Ian Anderson, CEO of Kinder Morgan, gestures during an interview at the company’s offices in Calgary in 2016. (THE CANADIAN PRESS/Jeff McIntosh)

Shovels could be in the ground on Trans Mountain by September, CEO says

Ian Anderson points to weeks likely required for NEB to reinstate 2016 regulatory record

The CEO of the Crown corporation building the Trans Mountain pipeline expansion says shovels could be in the ground by September following cabinet approval Tuesday of the long-delayed project.

Oil could be flowing in new segments of the pipeline between Edmonton and the West Coast by mid-2022, Ian Anderson said, about one year later than the timeline envisioned last August when the Federal Court of Appeal quashed its regulatory approval and halted all fieldwork.

“We’re excited, our shippers are excited and the communities we touch are excited along the pipeline corridor,” said the CEO of Trans Mountain Corp. during a conference call Wednesday.

“We’re confident now that our project will meet every standard, every regulation, every test and reflect the values and priorities and principles that we all care for as Canadians.”

The National Energy Board is being asked to reinstate the record from the previous regulatory proceeding in 2016 so that the project can be brought back to the same state of construction readiness as last summer, Anderson said, a process expected to take some weeks.

He said the fact the federal government owns the pipeline won’t change or hurry the process.

Two re-routing requests are still to be decided, he said, including one involving B.C.’s Coldwater reserve, although those processes aren’t expected to affect the timeline.

He said contractors are being mobilized, pipe is being stockpiled in yards in Alberta and B.C. and the Burnaby terminal on the West Coast is being made ready so that construction work can begin there as soon as permitted.

Anderson said there is no update on the last estimated project cost of $7.4 billion, while conceding that “time is money.”

Earlier Wednesday, Finance Minister Bill Morneau told a Calgary business audience the best way to convince a skeptical oilpatch that the expansion will actually be built is to go ahead and build it.

“What we said yesterday was that we renewed that (pipeline) approval,” Morneau told reporters.

“What’s happening today is we’re back at work. The re-permitting is happening starting today. We are going to get work going this construction season. I want people in Alberta and people across the country to know that intent is real.”

Last August, the Federal Court of Appeal ripped up the original federal approval of the 590,000-barrel-per-day expansion, citing incomplete Indigenous consultations and a faulty environmental review.

Dan Healing, The Canadian Press

Like us on Facebook and follow us on Twitter

Just Posted

Latest round of Columbia River Treaty talks wrap up in Cranbrook

Federal, provincial, U.S. and Indigenous representatives recently met for eight round of discussions

First Nations given max compensation for Ottawa’s child-welfare discrimination

2016 ruling said feds didn’t give same funding for on-reserve kids as was given to off-reserve kids

‘Staring at me:’ Oldest known spider ancestor found in B.C.’s Burgess Shale

‘I turned my head to the right and I see this glowing light coming from this rock’

More than 100 Water Guardians flood to Town of Golden council meeting

Submitted More than 120 people showed up to the Golden Town Council… Continue reading

Climate change website launched by Selkirk College and Columbia Basin Trust

The site features climate information for communities in the Columbia Basin and boundary region

VIDEO: Drone footage documents work to free salmon at Big Bar landslide

Video shows crews working to remove rocks and wood, and transporting salmon by helicopter

Defense says burden of proof not met in double murder case against Victoria father

Closing statements begin in trial for man accused of killing daughters Christmas 2017

B.C. dog breeder banned again after 46 dogs seized

The SPCA seized the animals from Terry Baker, 66, in February 2018

Surrey mom allegedly paid $400,000 for son in U.S. college bribery scam

Xiaoning Sui, 48, was arrested in Spain on Monday night

B.C. population on pace to fall behind Alberta

Provincial population could reach almost seven million in 2043, but Alberta is growing faster

Three dogs found shot dead in Prince George ditch

The three adult dogs appeared to be well cared for before being found with gunshot wounds, BC SPCA says

B.C. party bus company to be monitored after 40 intoxicated teens found onboard

Police received tip teens and young adults were drinking on party buses and limousines in Surrey

Rick Mercer calls out Conservative candidate in B.C. for fake meme

‘Not true. All fake. Please Stop,’ tweeted Rick Mercer in response

Bear killed in Kimberley after chasing girl, wreaking havoc on town

This particular brown-coloured bear has been the subject of many calls this summer; very food habituated, CO says

Most Read