Petronas LNG delay not due to B.C., Coleman says

Malaysian-led project still needs federal approval for site, CEO concerned about U.S. competition for gas exports to Asia

Lelu Island at the Prince Rupert port is the proposed location for an $11 billion LNG export terminal.

Malaysian oil and gas giant Petronas has put off its final investment decision on a large-scale liquefied natural gas project until some time in 2015, but it’s not because of B.C.’s taxes and conditions, says Natural Gas Development Minister Rich Coleman.

Pacific Northwest LNG, a consortium led by Petronas for a pipeline and terminal at the Prince Rupert port, issued a statement Wednesday citing construction costs and federal approvals it still needs for a pipeline and plants worth $36 billion.

“Costs associated with the pipeline and LNG facility remain challenging and must be reduced further before a positive final investment decision can be undertaken,” the statement says. “At the same time, Pacific Northwest LNG will continue to work to secure necessary regulatory and other approvals from the government of Canada.”

Coleman said he was consulted on the statement and remains optimistic about the project going ahead. The province set its tax and greenhouse gas rules for LNG projects during the fall legislature session, and completed agreements with the Nisga’a Nation to allow a gas pipeline to pass through their territory to the coast.

“It was always clear that once they got our piece completed, they would move on to making sure their numbers across the board with their partners work,” Coleman said. “That’s the pipeline, the upstream cost for gas plants, that’s the LNG plant itself, which they would build in Port Edward.”

Petronas CEO Shamsul Azhar Abbas said the decision will be made as soon as possible.

“This is vital in light of the current intense market environment and for Pacific Northwest LNG not to lose out on long-term contracts to competitive United States LNG projects,” Abbas said.

NDP natural gas critic Bruce Ralson called the decision “a setback,” noting that BG Group also cited U.S. competition in its recent decision to delay a final decision on its project for the Prince Rupert area.

 

Just Posted

More burning prohibitions rescinded in southeast B.C.

Category 2 and 3 fires will be permitted in Southeast Fire Centre as of 1p.m. on Wednesday.

Candidates declared for 2018 elections

Nominations for the municipal election have come to a close, and the… Continue reading

Summerland Steam lose one, win one in hockey action

Junior B team loses to Golden, but wins against Chase

Your Mountain Minute for September 13

Golden’s weekly 6-second news recap… Continue reading

B.C. RCMP turn to Const. Scarecrow to shock speeders into slowing down

New addition will watch over drivers from a Coquitlam median for first-of-its-kind pilot in Canada

B.C. home to 1/3 of Canada’s overdose deaths in first 3 months of the year

There were 1,036 overdose deaths in the first three months of the year, with 94 per cent accidental

B.C. candidate moves from hospice care to council race

He beat terminal cancer twice and entered hospice when he decided to run for council.

Canadian tobacco exec pushes back against vaping health concerns

A warning from Interior Health about the unknown health risks of vaping is getting a partial rebuke

Ministry of Agriculture commits $300,000 to help B.C. farmers obtain land

B.C. Land Matching Program supports access to affordable farmland for young farmers

Canadian air force short 275 pilots

Attrition outpaces recruitment and training claims Air Force

Teacher suspended after physically shushing, saying ‘shut up’ to student

Grade 5 student reported feeling ‘confused and a little scared’

A B.C. society helps to reforest Crown land after wildfires

Forest Enhancement Society of BC focuses on wildfire mitigation and the reforestation

Most Read